We do not publish a single headline rate, because any number quoted without a size, a material and a site is misleading. Instead we explain exactly how the price is built up, so you can read and compare any quotation intelligently, even if you do not work with us.
How shades are priced
Shades are priced per square metre: area multiplied by a rate, then adjusted for site conditions. The rate itself is set by four things:
- Cover type: HDPE mesh, PVC fabric, PVDF, polycarbonate or Shinko; each is a separate line in the quotation with its weight or thickness stated, because the material sets the life, appearance and maintenance, not just the look.
- Steel sections: selected for the clear span, height and wind load. Longer spans need heavier sections, and the section size is written into the quotation so it can be checked on site.
- Treatment and coating: hot-dip galvanising and powder coating are different line items; the difference is in life and rust resistance, and the treatment must be named explicitly.
- Foundations: fixing to existing concrete and excavating and casting new bases are different jobs; the site visit establishes which applies and it is written as its own line.
Which factors change the quotation lines?
| Factor | What we check at the site visit | The quotation line affected |
|---|---|---|
| Area | Number of vehicles and the usable area after setbacks and walkways | Fabric and steel quantities and the number of columns |
| Span between columns | Whether mid columns are possible or a clear span is required | Steel sections and foundations |
| Height | Whether SUVs, vans or small trucks pass underneath | Column length, sections and foundations |
| Cover | Ventilation needed, rain protection and the appearance from the street | Fabric or panel type and its thickness |
| Site and access | Working at height, a narrow entrance or the need for a crane | Installation and transport |
| Extras | Lighting, concealed gutters, special colours, solar panels | Separate lines, each stated on its own |
How tents and diwaniyas are priced
Tents are not priced per square metre in the same way, because the cost is split between fabric, frame and interior finishing. The items that set the price:
- Size, height, and the number of domes or arches.
- Outer fabric type and whether a decorated inner lining is included.
- Frame type (demountable or permanent) and the steel sections and their treatment.
- Interior finishing: flooring, panelling, seating, lighting.
- Systems: air conditioning, electrical, sanitary, thermal insulation.
- A permanent insulated diwaniya with AC and full finishing is a fundamentally different set of line items from a seasonal fabric tent, so the two quotations should not be compared with each other.
How to compare quotations intelligently
A large gap between two quotations for the same area always means a different line item, not necessarily that one of them is cheating. Ask these questions before you decide:
- What size and type are the steel sections? (not just 'galvanised steel')
- Is it hot-dip galvanised, or only powder-coated?
- Exactly which fabric, and at what weight or thickness?
- Are foundations included or extra?
- Are drainage and gutters included?
- What does handover include, and who follows up on snags afterwards?
- Does the price include delivery, installation and site cleaning?
A quotation that itemises these can be compared. One that says 'car parking shade, lump sum' cannot be evaluated and cannot be held to account later.
Get a price for your own project
We provide a site visit and measurement, then an itemised written quotation with a stated validity period. Send us your location and a photo of the area on WhatsApp and we will arrange the visit.
What does our engineer check at the site visit, and what should you prepare before it?
The site visit is not just a length and a width; it is the collection of the information that becomes the quotation lines. At every site we check:
- Area and setbacks: the usable area after walkways, doors and trees differs from the plot area on paper.
- Span and column positions: where a column can stand without blocking doors or vehicle movement.
- Ground and foundations: existing concrete, tiles over sand, or soil that needs new footings.
- Required height: the vehicle types, the boundary wall height and any overlooking neighbours' windows.
- Wind direction and drainage: where the shamal comes from and where rainwater goes once it leaves the shade.
- Access and working conditions: a narrow entrance, the need for a crane, or working inside an occupied apartment building.
- Existing services: cables, pipes and underground tanks along the footing line, so that excavation is done by hand where needed.
- Permits: inside the plot or on the pavement, residential or commercial, and whether the Kuwait Municipality approval procedure applies before work starts.
Before the visit it helps to have ready: photos of the place from the street and from inside, the number and type of vehicles, a shape you like if you have one, whether the ground is concrete, tiles or soil, and the date you want the work done. And if the shade is for a long row of cars, working out the shade area you actually need before the visit brings the first quotation closer to the final one.
How is the quotation built, line by line?
The quotation we hand over after the visit can be read line by line, because every line carries a specification that can be checked on site after installation:
- Site visit and measurement: visiting and photographing the site and recording everything in the list above.
- Fixing shape and size: agreeing the shade shape or tent type and the final dimensions, with a drawing where needed.
- Material lines: steel section sizes and their treatment, the fabric or panel type with its weight or thickness, and the foundation type.
- Work lines: workshop fabrication, transport, installation, drainage and gutters, and site cleaning, each on its own line.
- Extras: lighting, special colours, solar panels or side screens, shown separately so you can accept or decline each one.
- Terms: the quotation's validity period, the installation programme and the handover and acceptance terms, written into the quotation itself.
- Approval and scheduling: after you sign, the fabrication and installation dates are fixed and you receive a written programme.
Lump sum or itemised: which quotation can you actually compare?
An itemised quotation is the only kind that can be compared, and the only kind its author can be held to after installation; a lump sum is a figure without a specification. The difference, line by line:
| Line | In a lump-sum quotation | In an itemised quotation |
|---|---|---|
| Steel sections | 'Galvanised steel' with no size | Section size and treatment named |
| Cover | 'PVC fabric' with no details | Fabric type and weight, or panel thickness, and colour |
| Foundations | Not mentioned | A separate line stating the fixing method or footings |
| Drainage | Assumed | Gutters and run-off direction stated |
| Extras | Blended into the total | Each extra on its own line to accept or decline |
| Validity | Not stated | A validity period written into the quotation |
| Checking after installation | Not possible | Every line matched against what was built on site |
What wastes most of a client's time is asking for a figure over the phone for a shade nobody has seen, then comparing that figure with another contractor's itemised quotation. Other mistakes we see often:
- Comparing two totals without comparing the specifications line by line.
- Not mentioning that an SUV or a van will pass under the shade, so the height changes after quoting.
- Ignoring the rain run-off direction, so water pours onto the house entrance or the neighbour's yard.
- Choosing the fabric from a photo on a phone without seeing a sample in sunlight.
- Assuming foundations, drainage and cleaning are included without their being written down.
How do the season and Kuwait's conditions affect the quotation and the work?
Timing is a real factor in the quotation: it changes the duration, the availability of materials and the working hours possible, and its effect is written into the installation programme:
- Peak demand: the weeks before the camping season and the start of summer bring the highest demand for shades and tents, so supply and installation dates stretch, and this is stated in the programme.
- Summer heat: the midday ban on outdoor work in the summer months shortens the daily installation hours, so exterior work is scheduled for mornings and evenings.
- Shamal and sarrayat storms: fabric tensioning and lifting trusses are not done on a windy day, so the programme leaves a margin for wind and rain days.
- Coastal humidity: for sites near the sea we recommend a heavier steel treatment, stated as a specification in the treatment line.
- Permits: if the site needs Kuwait Municipality approval, the owner obtains it and fabrication is scheduled once it is granted.
From Our Work




Frequently Asked Questions
Why do you not publish a rate per square metre?
Because a rate quoted without material, span, height and foundation details is misleading. It can look final and then change through 'extras'. We prefer a site visit and an itemised written quotation you can actually compare.
How do the site visit and quotation work?
Our engineer visits, measures and photographs the site, and you then receive an itemised written quotation with named line items and a stated validity period.
Can the quotation lines be adjusted after I receive it?
Yes. Every line has alternatives: cover type, column layout, finish level and extras. We reissue the quotation with the alternatives you choose and explain what each one means for life, appearance and maintenance, so you decide.
Can the project be done in phases?
Yes, particularly on larger projects and commercial car parks, where we phase the work to suit your plans.
How long is a quotation valid?
Every quotation carries a validity period written into it, because the availability of steel and fabrics and their delivery dates change through the year, particularly before the camping season and the start of summer. After the period ends we re-check the lines and reissue the quotation to the same specifications.
Does the quotation include permits, foundations and drainage?
Foundations and drainage are each written as their own line: foundations according to what the site visit shows, drainage and gutters according to the shade shape. Permits are not part of the quotation: obtaining any Kuwait Municipality approval is the owner's responsibility. Anything not written in the quotation should not be assumed to be included, a rule we advise you to apply to any quotation you receive.
Does the season affect the quotation and the programme?
Yes. The season changes material availability, delivery dates and the outdoor working hours permitted in summer, so the installation programme and sometimes some of the lines change. That is why every quotation carries a written validity period, and we re-check it if that period ends before you approve.
Ready to Start Your Project?
Call us, send a WhatsApp message or email us to book a site visit and a clear written quotation.