In October 2026 the Shah Sawar team completed the full waterproofing of a commercial building roof in Kuwait City. The roof is full of the details where leaks usually start: HVAC unit bases, ductwork, a plant-room wall, a glass pyramid skylight, roof drains and vents. This article shows the project as it was carried out, step by step, with photos from the site during the work and after completion. It also explains why torch-applied bitumen membrane was chosen and how to tell whether your building or villa roof needs new waterproofing.

About the project
The building is a multi-storey commercial property in Kuwait City. Its roof carries the outdoor AC units and ductwork, a plant room and a glass pyramid skylight that lights the top floor. Like most commercial roofs in Kuwait, the old waterproofing had been through years of sun and heat, and weak points were showing at the joints and around the bases and drains.
The brief was complete waterproofing of the roof, including every existing detail, without removing the AC units or disrupting the building, using a system that stands up to high heat and to the regular maintenance traffic on the roof.

Why do commercial roofs leak in Kuwait?
A flat roof in Kuwait lives in hard conditions: surface temperatures above 50 degrees in summer, strong UV all year, then short, heavy winter rain that finds every weak point. Leaks rarely start in the middle of the roof. They start at the details:
- HVAC bases and ductwork: the most common leak point; the old membrane does not turn up the base, or cracks at the corner.
- Roof drains: if the membrane is not dressed into the drain, water runs between the membrane and the concrete slab.
- Skylights and openings: every opening in the roof needs an upstand and a sealed detail around its base.
- Overlaps between rolls: a poorly sealed overlap opens up with daytime expansion and night-time contraction.
- Maintenance traffic: AC technicians walk the roof all year, and any membrane without a protective surface suffers.
To see how these problems show up inside the building, read our guide to wall cracks and damp.
The system chosen: torch-applied bitumen membrane
For this roof we chose torch-applied modified bitumen membrane with a mineral-granule surface, for the following reasons:
| Property | Benefit on a commercial roof |
|---|---|
| Torch-sealed overlaps | Each overlap fuses with the neighbouring roll, so there is no open joint for water to enter |
| Mineral granules on the surface | Protect the bitumen from UV and reduce heat absorption, with no extra protective layer needed |
| Thickness and strength | Takes regular foot traffic for AC maintenance and light equipment movement |
| Flexibility of modified bitumen | Follows the roof's expansion and contraction between hot days and cool nights without cracking |
| Shapes with heat | Turns up bases and walls and forms tightly around drains and the skylight |
Other waterproofing systems and where each one fits are explained on our waterproofing and roof insulation service page.
How the work was carried out on site
- Roof inspection and survey: locating the old leak points, checking the falls towards the drains, and listing every base and opening that needs its own detail.
- Cleaning and preparation: removing dust and damaged membrane, cleaning the drains, and correcting any ponding by adjusting the falls.
- Primer coat: applied to the concrete deck and the upstands so the membrane bonds fully.
- Laying the membrane: the rolls are unrolled and torch-bonded across the whole roof, with every side and end overlap heated until a bead of bitumen shows at the edge, the sign of a full seal.
- Upstands: the membrane is turned up the HVAC bases, duct upstands, the plant-room wall and the skylight base, and sealed at the corner so no junction is left open.
- Drains and vents: the membrane is dressed into each roof drain and formed around each vent with additional torch-sealed pieces.
- Final check: every overlap, corner and base is checked by eye and by hand, any loose edge is re-sealed, then the roof and drains are cleaned.

The details that made the difference
What sets a commercial roof apart from an empty one is the number of details. On this project the critical points were:
- HVAC bases and ductwork: the membrane was turned up every base and duct and sealed at the corner, making each base part of the waterproofed roof rather than an island in the middle of it.
- Plant-room wall: the membrane was taken up the wall well above any likely water level.
- Glass pyramid skylight: sealed around its base on every side, because any gap here means a direct leak into the top floor.
- Roof drains: the membrane was dressed into each drain and sealed, so rainwater goes down the drain and not under the membrane.
- Vents: additional torch-sealed pieces around every vent.
The photos below are from the site itself, during the work and after completion:







How to tell your roof needs new waterproofing
- Damp patches or peeling paint on the top-floor ceiling after rain, especially near AC units or skylights.
- Water standing on the roof that does not dry within a day or two.
- Blisters, cracks or lifting in the old membrane, or open overlaps between rolls.
- Old waterproofing that has gone many years without an inspection.
- A noticeably hotter top floor and higher AC running costs; a new membrane with reflective granules reduces heat absorption.
The best time to inspect the roof is before the rainy season. Repairing before the first rain is far easier than dealing with a leak once it reaches the decor and the electrics.
The same system for villas and residential buildings
The same steps apply to a villa or apartment-building roof, with one difference: a villa usually has fewer details, but they matter just as much. AC unit bases, roof water tanks, the stair bulkhead and the drains all need the same upstands and sealing. If the roof will be used as a seating area, we add a protective layer or tiles over the membrane.
Waterproofing is part of our renovation and maintenance work and is often done together with a villa renovation in the right order, as explained in our villa renovation guide.
Shah Sawar Building Construction Company carries out roof waterproofing for commercial and residential buildings with its own team, from inspection and preparation to torching, detailing and the final check. Book a site visit: we inspect your roof and send you a written, itemised quotation. More of our work is on the projects page.